CASE STUDY : RIPPLEYVILLE ESTATE - BRADFORD, WEST YORKSHIRE

Updated: Jun 9

Location: Ripleyville Estate, Bradford BD5 7TX

Commenced: October 2022

Estimated Completion: 24 Weeks

Actual Completion: 22 Weeks

Project Details

Allclear Demolition was tasked with the complete demolition, including slab and foundation removal, with material repurposed on-site in order to make prepare the site for 73 new properties.


Work Challenges & Solutions:

  • Preplanning:

    • Asbestos Surveys and Removal: Conducted by a subcontractor to ensure safety and compliance.

    • Service Disconnections: Successfully identified and marked underground services to prevent disruptions during demolition.

  • Internal Soft Stripping:

    • Recycling: Achieved a high recycling rate of 90% for materials like plasterboard and timber.

    • Safety Measures: Addressed the presence of 'sharps' with thorough needle sweeps, ensuring safety for operatives.

  • Sequencing:

    • Coordination: Prioritized tasks to enable smooth asbestos removal, soft stripping, and structural demolition in tandem.

    • Toolbox Talks: Conducted weekly briefings with visual plans to maintain clear communication among all site operatives.

  • Structural Demolition:

    • Machinery Use: Deployed 30-tonne and 20-tonne excavators with specialized attachments for efficient demolition.

    • Material Processing: Processed concrete and other materials on-site to produce 6F2 aggregate, used for future construction.

  • Crushing Operations:

    • Aggregate Production: Started in January 2023, using mobile jaw crushers to process arisings into high-quality 6F2 material for reuse. Grading tests of aggregates proved to be of high quality. 6F2 material was stockpiled on site for use by the construction contractor.

Achievements

  • Exceptional Planning and Communication: Effective project management and coordination were key to the timely and safe execution of tasks.

  • Ahead of Schedule: Completed the project two weeks ahead of the estimated timeline.

  • Commendations: ESH Construction praised Allclear Demolition for their diligent work and leadership throughout the project.


Allclear Demolition demonstrated high standards in project management, resulting in commendations from our client for Allclears diligence and efficiency.